The Select Board reviewed a smaller design for the Public Safety Building, about 15,300 square feet. It keeps key functions such as decontamination access and vehicle exhaust systems. Wetland and stormwater concerns were addressed through design changes and possible mitigation. Plans, renderings, a website and FAQs will be available on Election Day to inform the public.
How it happened
Feb 12 · MinutesFirst mention
Committee members discussed steps for planning a public safety building: space needs assessments, site selection, budgeting, and funding. They said funds for early design and engineering are needed before town votes. Examples from other towns ranged from $10,000 to $64,000. A member shared research on Candia, Brookline, and Plymouth and suggested contacting other towns. The police chief and a police lieutenant reported that grants exist, but eligibility often depends on project readiness and community makeup. The committee said planning steps should be done before applying. A member described towns using warrant articles (questions voters decide) to build dedicated capital reserve funds over time. The committee also listed tasks. The lieutenant will expand a spreadsheet of comparable public safety buildings, with size, cost and features. One member will keep researching other towns.
Mar 12 · Minutes
At the March 12, 2026 meeting, the committee's warrant article (a question put to voters) passed with a strong majority, so funds are now available. The committee talked about making a plan for how to use the funds. The select board is the agent for the funds and must approve any proposed actions. The committee will present its plan to the select board.
Mar 12 · Video
The chair said the warrant article for the public safety building passed with good numbers. The committee now has funds and needs a plan for next steps.
Mar 26 · Video
The chair said the committee has not heard back on other properties it asked about. He expects some answers, but does not know how soon. One owner might respond this spring or summer. The chair said the Route 87 location still seems ideal. The select board's representative is to ask the town's attorney about the process going forward, such as design-build and construction management. He had not yet done so.
Mar 26 · Video
A member said Plymouth's chief told him Plymouth was just approved to buy 4.9 acres for $850,000. The member said the price had been $900,000. The land has water and sewer nearby. A member said the Newfields site could save roughly three-quarters of a million dollars because the town already owns it. The engineer said the state may take that into account when it reviews permits, since this is a public safety building.
Mar 26 · Minutes
A member said the committee has not yet heard back about inquiries on other properties. He expects updates in the coming months. The Old Lee Road site is the most likely location now. Two members said the state may look favorably on the project because the town already owns the land. This could ease permitting and reduce the need to buy land.
Apr 7 · Minutes
The chair said the Public Safety Building Committee finished a wetland delineation (a survey marking wetland edges) last week. It cost $800, below the earlier approved limit of $1,000 to $1,500. The committee is looking at four parcels, including a larger 11-acre lot now under detailed review. The chair spoke with the town attorney about the lots and noted a possible issue he expects to be fairly simple to resolve. He will raise it at the committee's next meeting.
Apr 16 · Minutes
The committee discussed the early stage of the project. $50,000 was approved earlier for site selection and first-draft (conceptual) plans. Members said they want to use it well, including surveys and engineering, so they do not have to ask voters for money again and again. Members said a formal needs assessment is needed to set the building size, features and whether the site works. The architect offered to help with a scope and block plans. She estimated construction costs rise about 10% each year. A member asked about yearly cost increases. Members suggested contacting firms such as Ricci and Turner Group. The architect will send a follow-up email with a checklist and questions, and an outline proposal with cost estimates for each phase.
May 21 · Video
A member told the committee that Raymond is working on a police-only building of 15,800 square feet. Raymond had a $6.8 million estimate about 6 years ago and has land, drawings and a needs assessment. It hopes to be on the ballot next year. Members said it might now cost $12 to $13 million. They also said Exeter's project failed in 2023 at $16.5 million and later passed at $17.5 million with about 2,000 fewer square feet. Members said this kind of cost data can be shown to the public.
May 21 · MinutesDecided
Members looked at recent public safety building projects in Raymond and Exeter. A member said Raymond's police building is 15,800 square feet and its cost rose from $6.8 million to over $12 million. The member said this shows why early needs assessment and drawings matter. Another member described Exeter's failed and successful ballot votes, cost increases and cuts in square footage. The member said inflation and timely execution affect cost. The committee voted unanimously to approve the April 30 and May 6 minutes as amended and to adjourn at 6:32pm. Upcoming meetings were set for June 3 and June 17.
No vote on this item. Separately, the committee approved the April 30 and May 6 minutes as amended, and voted to adjourn, both unanimously.
Jun 9 · Minutes
The chair summarized a recent Public Safety Building meeting. It covered the request for qualifications and proposals process (RFQ/RFP), the timeline, scope of work, responses from interested firms, and the need for a concept design and needs assessment. The committee said land use and environmental professionals should check the site's space and limits, which will help set the building's size and layout. The chair estimated that delays could add about $500,000 to $800,000 per year in costs from inflation and said the project should move quickly. The next meeting will review the proposals received and start the design-build RFP process for the concept design and needs assessment. No board vote was recorded.
Jun 24 · Minutes
The committee reviewed the project phases and how site engineering connects to the needs assessment (a study of what space the departments need). Members said the building's size and layout depend on how much land can be used. They said again that the work should stay within the money already set aside and avoid asking the town for more. Ways to control costs included phased contracting and clear communication with consultants. The committee plans to line up the choice of a site engineer with the needs assessment and conceptual design RFPs (requests for proposals). A member asked if a recently submitted second RFQ (request for qualifications) should have been an RFP, to avoid follow-up interviews. Members said they want a construction company that can work with the geotechnical (soil and ground) work, not an architect alone. This will be discussed more at the next meeting.
Jun 30 · Minutes
The Select Board representative said that missing the March deadline could add $800,000 to project costs. A member said the consultant expects to finish surveying and flagging (marking boundaries and features on the site) within three to four weeks of starting. The consultant was ready to begin once notified.
Jul 14 · Minutes
Public Safety Building committee update
Jul 22 · Video
The committee discussed putting the public safety building on the town warrant (the list of questions voters decide). It will need a bond (borrowing money) hearing before the warrant goes up. A member said the notice for the bond hearing for a March 27 vote must be posted no later than the 3rd Tuesday in January. The warrant must be posted on or before the last Monday of January. The chair said a timeline of legal requirements for the notice, bond hearing and warrant would be drawn up. The team said it wants as much information as possible by September or October, with a target of the end of October, to allow public input before then. A member said the committee still needs phase two, a needs analysis and concept design, and cannot do it until it knows the lot can be built on.
Jul 22 · Minutes
The committee planned the timeline ahead of the March vote. The chair said the committee needs as much project information as possible by September or October for public input and legal deadlines. Northam Survey estimated field survey work could start the first week of August, with a draft plan by early September. Beals Associates could then make concept layouts within two to three weeks of getting the survey data. The chair said the public hearing notice for the bond must be posted by the third Tuesday in January. The warrant must be posted before the last Monday in January. The chair also said the committee should not use up its available funds on survey and wetlands work before confirming the site is suitable. That would leave money for the needs analysis and concept design.
Aug 12 · Minutes
On 8/12/2026 the committee met with teams from Turner Group, Tecton Architects, Martini Northern, Placework and Jobin Construction Consultants. They talked about how to plan a new public safety building (police and fire) and bring a proposal to town voters. The chair said the goal is a site, a concept design, a needs assessment and a cost estimate, all within a set budget. About $50,000 was set aside for pre-design work, and $30,000 to $35,000 of that remains. The group said the site needs a survey and soil tests, and that space needs must be set before design starts. Turner Group and Placework offered to help with public meetings and presentations. Placework showed a short schedule that starts in September. It calls for the needs assessment, concept design and budget to be done by November, so the item can go to the March town vote. This will take frequent meetings and active help from all stakeholders.
Aug 25 · Minutes
The chair reported that SMP Architecture was chosen to lead planning for a new public safety building. The site is about 14 acres of town-owned land near Route 87 and Meadow Road, with about four to five acres that may be suitable. The project will move ahead with a needs assessment, site review, programming and community input. Wetland and boundary surveys are underway. The Town plans to limit wetland impact and the building's overall footprint.
Sep 15 · Minutes
The chair reported on the September 2, 2026 Public Safety Building meeting, which about 20 to 25 residents attended. Fire and Police first planned a building of about 17,000 square feet, and a review is underway to see if it can be smaller. The building would serve Police, Fire and Emergency Management and could also be used for emergency shelter, cooling and warming, and power outages. Environmental and wetlands studies are done and are being reviewed with the architect. The proposed site is about 14.2 acres, and 3 to 4 acres may be needed for the building. The group talked about conserving the rest and adding access from Meadow Road. The chair also said the Town may be able to host an ALS (advanced life support, paramedic) response vehicle, which could speed up response and bring rental income.
Sep 21 · Minutes
The Safety Building Team proposes to use town land on Piscassic and Meadow. The land is not under an easement now. The team proposes to put the remaining land around the building under some kind of easement. No vote was recorded.
Sep 21 · Agenda
The commission will hear an update on a land use proposed by the Safety Building Team.
Oct 13 · Minutes
The chair reviewed updated plans for the Public Safety Building. The building size was cut to about 14,000 to 15,400 square feet. The town-owned property was confirmed as the only workable site. The committee is working to limit harm to wetlands and to address neighbors' concerns with landscaping, limited emergency lighting and the direction vehicles face. Residents were encouraged to review project information online and attend upcoming committee meetings.
Oct 27 · Minutes
The Select Board reviewed a smaller design for the Public Safety Building, about 15,300 square feet. It keeps key functions such as decontamination access and vehicle exhaust systems. Wetland and stormwater concerns were addressed through design changes and possible mitigation. Plans, renderings, a website and FAQs will be available on Election Day to inform the public.